The deputy director of Vietnam’s Biggest Airport project management board, Nguyen Khac Phong revealed that by next month, they would be able to hand over a clear site for the construction of the passenger terminals. 

The project began in January last year, following years and years of length land acquisitions and preparations. In February this year, after approximately a year of work, only demining and fencing had been done to completion. This caused Pham Minh Chinh, the Prime Minister to express dissatisfaction with the project’s progress.

The project’s slowed pace is however attributed to Dong Hai province’s delay in the handing over of cleared and prepared designated land for the project. 