The construction progress of the new terminal Jorge Chavez Airport that serves Lima, has reached a 98,91% with driving projection 37,7 million passengers per year.
According to the technical report, presented during the 83rd session of the national Airport Users Council, the Terminal Building (2100) presents a preview of 99,70 %. In outdoor and support areas, the Field of Services (2200) register a 99,97 % general execution, with a 100 % at the Water Management Center, Fuel Tank, Main Substation and Chilled Water Plant. For his part, the Santa Rosa area (2300) reaches the 99,15 %, including viaducts, arrival paths and cycle paths 100%...