Hindustan Times
Vinod Rajput
25 June 2024
NIAL has informed the Uttar Pradesh government that about 78.11% work on Noida airport has been completed, but the project stands delayed.
The Noida International Airport Limited (NIAL), the government agency overseeing the construction of the greenfield international airport in Jewar, has informed the Uttar Pradesh government that about 78.11% work on Noida airport has been completed, but owing to the slow pace of work on the terminal building, the project’s completion deadline of September 29, 2024, has been deferred by seven months, said officials in the know of the matter on Monday.
Now, Yamuna International Airport Pvt Ltd (YIAPL), the concessionaire, has rescheduled the completion date from September 29, 2024, to April 2025, said these officials.
[Read on: Jewar airport to be delayed by 7 months: Officials | Latest News India - Hindustan Times]