Turner Construction delivered the new Terminal 1 baggage handling system at San Diego International Airport.

The final baggage handling contract was approximately $95 million.

Early procurement and contractor involvement reduced the package by about $45 million from an initial market projection.

The system was activated without affecting the Sept. 23, 2025, Terminal 1 opening.

Testing recorded 99.7% tracking accuracy during TSA integrated system acceptance testing...

Turner Cuts San Diego Airport Baggage System Costs to $95M - Construction Owners - 19 August 2026