Back in May the first round of construction wrapped up, which included adding two more gates for a total of six,  a full service restaurant and a frequent fliers lounge.

Director of Communications Rachel Barth says walls and flooring are being installed for the new administrative offices, which are scheduled to be finished in January.  She says there will also be a new board room and a community room that can accommodate 100 people. 

Barth says that work should be completed in January or February.  Two new baggage carousels will  also be added and are expected to be operating in May.