A team of more than 200 engineers and technicians are halfway through a five-month project to resurface London Stansted Airport.

Work on the 1.9 mile-long (3km) runway - equivalent to the size of 25 football pitches - has to be timed meticulously overnight while fewer flights are scheduled.

The engineering firm Lagan began the project on 8 January and is aiming to complete by 6 June.

The to-do list includes:

  • Lay approximately 65,000 tonnes of asphalt
  • Replace about 1,500 runway lights with more energy-efficient LED bulbs
  • Lay about 62 miles (100km) of new cabling