Montréal-Trudeau International Airport
05 Oct 2025
As ADM Aéroports de Montréal continues to implement Flight Plan – its development plan to modernize the infrastructure of YUL Montréal-Trudeau International Airport to improve accessibility and connectivity – an important milestone will be reached with the upcoming closure of the multi-level parking facility and the P5 lot located in front of the terminal. The structure, which is nearing the end of its useful life, and the adjacent parking lot will close to the public on October 15
Demolishing the multi-level parking facility is necessary to add lanes to the existing drop-off and pick-up areas in front of the airport terminal. These areas will ultimately see their capacity tripled, which will improve traffic flow on the site. The new multi-level parking, which will offer 6,300 spaces, is expected to be completed in 2031. It will have an additional underground level to accommodate 1,200 vehicles