San Antonio Express-News
Richard Webner
20 August 2026

The proposed upgrades for terminals A and B are part of an effort to modernize San Antonio International Airport, in addition to new Terminal C construction.

San Antonio’s City Council on Thursday approved a $220.5 million contract to renovate the two existing terminals at San Antonio International Airport — a project which, along with the ongoing $1.7 billion construction of a third terminal, is designed to lift the airport into the big leagues.

Manhattan-Joeris, a joint venture between Joeris and the Manhattan Construction Group, won the contract...The renovations to the 378,524-square-foot Terminal A..and the 231,753-square-foot Terminal B...will be financed by issuing bonds that will be paid off with revenue generated by the airport...

Council approves $220.5M contract for renovating airport terminals - San Antonio Express-News - 20 August 2026

Not a member?
Take a look at our member benefits