Port Polska is moving ahead with the next phase of its investment programme. The company is carrying out works at the site of the future airport, constructing the High-Speed Rail tunnel in Łódź and preparing the road network around the port. The Multiannual Programme for 2024–2032 provides for expenditure of PLN 131.7 billion.
The scale of the programme is also reflected in the number of procurements being launched: by the end of September, the company had initiated 31 investment procurement procedures worth more than PLN 14 billion, with further procedures planned by the end of the year. Financial expenditure related to the company’s investments and operations has reached PLN 7.42 billion.
- Finance: PLN 7.42 billion – the total amount spent on investments and the company’s operations, from all sources of financing, as at 31 July 2026.
- Airport: the company is preparing the terminal foundations and construction facilities, while carrying out contracts covering the terminal design and baggage handling system.
- Rail: work is under way on the High-Speed Rail tunnel in Łódź. The company is also preparing to construct further sections of new railway lines.
- Roads: the company is preparing the airport’s connection to the public road network, as well as an investment involving the construction and reconstruction of national, county and municipal roads around the port, with a combined length of approximately 90 km...