Nashville International Airport (BNA) is set to begin an 18-month renovation of its Central Core terminal to prepare for projected increases in passenger numbers over the next decade.
..the Central Core Enhancement is a 40 million USD project aimed at expanding terminal entrance areas and improving passenger flow.
Key changes that will be implemented as part of the project include:
- Increasing the number of escalators from six to sixteen to connect ground transportation, baggage claim, ticketing, and the BNA Plaza more efficiently.
- Adding a third elevator and upgrading the two existing elevators with larger, faster models, effectively doubling overall capacity.
- Building additional capacity and flexibility to maintain terminal operations during peak periods...